Over recent months, the Capaccioli Group has successfully installed or commissioned several machines and plants:

› Test run at Cersanit

In July 2012 the preparation plant at Cersanit, Romania, was tested. Machines supplied to this plant included box feeders, FD6010 clay crusher, LS1008 roller mill, LF 1210 fine roller mill with 0.6 mm fineness, MF400 mixer, M450/S extruder, grinding plant for chamotte with 0.4 mm fineness. The quality and production targets have been reached fully.

› Automatic plant tested at Kilsan

In November 2012 the new line that had been supplied on schedule to Kilsan, ­Turkey, was tested on site. The scope of supply includes two cutting lines that feed a programming bench. A robot with a light alloy gripper loads the products onto the dryer steel pallets. The line has a capacity of 18 000 pieces/h.

› Supplies to Naili ­completed

Supplies for the complete plant of Briquetterie Naili with a capacity of 200 000 t could be completed on schedule in November 2012. Assembly is already at an advanced stage. Start-up is scheduled for June 2013.

› Start-up of the 400 000-t plant for Messaud

The complete plant near Bouira has entered in its start-up phase. Production start is scheduled for April 2013. The scope of supply includes one clay preparation line, two production and extrusion lines, two kilns, two dryers, automatic setting system, kiln unloading, packaging lines and machines for loading trucks.

The latest version of the FD6015 clay crusher has recently been installed at ­Capaccioli’s production line in Sinalunga. The machine is suitable for use as the first process stage in clay preparation lines. In line with ­Capaccioli’s corporate policy, for this machine, state-of-the-art technologies and high-quality materials have been used and renowned suppliers contracted.

x

Related articles:

Issue 09/2012

Capaccioli presents Super Fine roller mill

With the addition of the Aral series machines for clay preparation to its product portfolio, ­Capaccioli is presenting itself to the world market as a flexible supplier of turnkey plants. These are...

more
Issue 05/2014

Capaccioli

For the period 2014–2015, Capaccioli is presenting previews of its new products based on its strategy of the vertical integration of the design and production process. 1 Dry clay preparation...

more
Issue 08/2009

Successful commissioning of new plants by Capaccioli

Start of production at Ceramica S.A. in Iasi Capacciolimpianti announces that the new production plant for bricks of the Brikston brand supplied to Ceramica S.A. in Iasi, Romania, has been...

more
Issue 4/2016

Capaccioli starts Zozik brick plant project in Erbil

In March 2016, the first deliveries for the “Zozik Brick Plant” project were sent on their way. The first 32 trailers arrived on site in Erbil where site operations for plant construction are...

more
Issue 11/2013

Capaccioli s.r.l. starts up new brickworks for Sarl Banou Messaoud

Capaccioli, the Italian plant engineering company, recently commissioned a new plant for the Algerian brick producer Banou Messaoud. At this plant, one of the largest brickworks in Algeria,...

more